Delivery times for transformer components

Standard delivery times from Ludvika, Sweden.

The delivery times below reflect our general load situation. However, we reserve ourselves for large orders received during the period in between, which might affect actual delivery time. 

Shorter delivery times are also available but are subject to material availability. Please contact our Sales Department if the indicated delivery times do not meet your requirements and material availability. 

Please note that final delivery times are always as per the order acknowledgment.

Present Preliminary Delivery Times (Updated as of May 30, 2025)

TAP-CHANGERS
UB 22 weeks (+4 weeks with BUE)
UZ 27 weeks
UCG 52 weeks (+4 weeks with BUE)
UCL 52 weeks (+4 weeks with BUE)
UCC/UCD on request
VUBB 22 weeks (+4 weeks with BUE)
VUCG 52 weeks (+4 weeks with BUE)
VUCL 52 weeks (+4 weeks with BUE)
BUSHINGS  
GOB+ 40 weeks
GOB 1050 35 weeks
GOE ≤1675 35 weeks
GOE 1800 35 weeks
GOE ≤2550 on request
GOE 2600 on request
GOE(2) ≤1425 35 weeks
GOE(2) 1675 35 weeks
GOEK on request
GOH 15 weeks
GSA-OA/ARF AF/ED ≤170 52 weeks
GSA-OA/ARF AF/ED 245 52 weeks
GSA-OO 52 weeks
GSB 245 34 weeks
GSB 362 38 weeks
GSB 420 39 weeks
GSB 550 on request
GSB 800 on request
GSBK 44 weeks
ARF 245 36 weeks
ARF 300 36 weeks
ARF 362 36 weeks
ARF 420 44 weeks
ARF 550 on request