Plazos de entrega para componentes de transformadores

Standard delivery times from Ludvika, Sweden.

The delivery times below reflect our general load situation. However, we reserve ourselves for large orders received during the period in between, which might affect actual delivery time. 

Shorter delivery times are also available but are subject to material availability. Please contact our Sales Department if the indicated delivery times do not meet your requirements and material availability. 

Please note that final delivery times are always as per the order acknowledgment.

Present Preliminary Delivery Times (Updated as of February 18, 2025)

TAP-CHANGERS
UB 16 weeks
UZ 24 weeks
UCG 38 weeks
UCL 38 weeks
UCC/UCD on request
VUBB 16 weeks
VUCG 38 weeks
VUCL 38 weeks
BUSHINGS  
GOB 34 weeks
GOB+ 40 weeks
GOB 1050 33 weeks
GOE ≤1675 33 weeks
GOE 1800 33 weeks
GOE ≤2550 on request
GOE 2600 on request
GOE(2) ≤1425 33 weeks
GOE(2) 1675 33 weeks
GOEK on request
GOM 33 weeks
GOH 15 weeks
GSA-OA/ARF AF/ED ≤170 40 weeks
GSA-OA/ARF AF/ED 245 40 weeks
GSA-OO 40 weeks
GSB 245 33 weeks
GSB 362 33 weeks
GSB 420 35 weeks
GSB 550 on request
GSB 800 on request
GSBK 34 weeks
ARF 245 34 weeks
ARF 300 34 weeks
ARF 362 34 weeks
ARF 420 38 weeks
ARF 550 on request